We will continue our environmental investigations and design of the project.  

We are seeking funding for right-of-way and construction as opportunities present themselves.  

 
  • Project identified in the Basalt Creek Transportation Refinement Plan

    2012-2013
  • Design studies and alternatives analysis

    March 2019-January 2022
  • First prioject open house

    June 11, 2019
  • Second project open house

    October 23, 2019
  • Preliminary design

    January 2020-June 2022
  • Environmental reports and permitting

    July 2020-August 2023
  • Third project open house

    Feb. 25-March 13, 2022

    You are here

  • Final design

    June 2022-June 2024
  • Right-of-way acquisition

    January 2023-September 2024

    Dependent on funding.

  • Begin construction

    January 2025

    Dependent on funding.