This open house was active from Feb. 25-March 13, 2022. Information on this website may no longer be current. Email us for more information.
We will continue our environmental investigations and design of the project.
We are seeking funding for right-of-way and construction as opportunities present themselves.
-
Project identified in the Basalt Creek Transportation Refinement Plan
2012-2013 -
Design studies and alternatives analysis
March 2019-January 2022 -
Preliminary design
January 2020-June 2022 -
Environmental reports and permitting
July 2020-August 2023 -
Third project open house
Feb. 25-March 13, 2022You are here
-
Final design
June 2022-June 2024 -
Right-of-way acquisition
January 2023-September 2024Dependent on funding.
-
Begin construction
January 2025Dependent on funding.